How Long Does it Take to Develop a Custom Medical Cart?

Posted by Shannon Pelky on October 21, 2026

One of the first questions we usually get asked about custom medical cart design is, “How long will it take?” The answer often depends on whether a customer wants a standard medical cart or a fully custom cart but can vary even more depending on specifications. To give a general overview of the development process and to try to answer the question of "how long will the medical cart development take?" we give an overview of the development timeline.

Development Process Overview

Visual of the Time it Takes to Develop a Custom Medical Cart

At HUI, medical cart development moves faster than many customers expect. Our unique approach and an experienced, collaborative design team keep our average development timeline to just a few months. Below is an overview of what happens at each stage, so your team knows what to plan for. 

Concepts (4 weeks)

Custom Medical Cart Concepts Take 4 Weeks to Complete

Discovery Meeting: 

We start the concept stage with a Discovery Meeting, where the HUI team works with your team to fill out a “Features and Functions Worksheet” with all of your project requirements. Additionally, we cover where the cart will be used, the desired look and feel, your preferred caster type, and shipping methods. 

Concept Generation:

 Our industrial designer sketches concepts while our project manager develops tooling and production cost estimates, so design and budget stay aligned from the start 

Concept Refinement:

Next, we will present three to five industrial design concepts so your team can choose their preferred design features. This meeting gives you the flexibility to mix and match concepts, tooling options and any other information brought to the table.


Final Concept:

Once we have a definitive understanding of the cart you want, HUI’s design team will put together a polished final concept for your approval before engineering begins.


Cart Development timeline - engineering-2

Engineering (8-10 weeks)

 

The engineering phase is where your custom medical cart becomes a manufacturable product.

Design Engineering:

Our engineers convert the approved, final concept into a production-ready cart design.

Customer Review Meetings:

We will hold regular engineering review meetings with your team throughout this stage to review the models and make sure everything meets your expectations. 

Analysis and Testing:

Before anything is built, our engineers run virtual analysis to determine the angle at which the cart will tip, the maximum load a shelf can hold before deforming, and more. 


DFMEA Meeting:

We hold a DFMEA meeting to identify design risks, answer open questions, and define the testing the cart will need once a production-grade prototype exists. 


Cart Development timeline - production grade prototype and functional-2

Prototyping (4-6 weeks)

 

Full-Scale Print (Optional):

If your team would like, the engineers can produce a full-scale print of the design for review. 


Manufacturing and PFMEA:

We create prints and assembly instructions for the manufacturing floor. Once they’re complete, we hold a PFMEA (Process Failure Mode and Effects Analysis) meeting to evaluate risks in the manufacturing process. 


Functional Prototype (Optional):

When needed, we build a functional prototype, often just a skeleton or a portion of the cart, to prove how the design works in the field while keeping costs down by deprioritizing aesthetics. If your project involves simple changes to a standard cart, or a custom cart very similar to one we’ve built before, you may not need this step. 


Production-Grade Prototypes:

Lastly, we build a prototype that closely matches the finished cart in both function and appearance. It’s ideal for spotting trouble areas, and it undergoes initial packaging tests and IEC 60601-1 testing.


IEC 60601-1 Testing (Optional): 

We offer preliminary IEC 60601-1 testing and initial packaging testing for any customers who would prefer to utilize our team’s resources instead of their own facilities. For our team, 60601 testing takes about two days.

What Can Extend Your Medical Cart Development Timeline?

Your schedule can shift based on:

  • Lead times for specific manufacturing processes and materials
  • The number of concept iterations
  • Design changes during development
  • Customer decision-making time
  • Time needed to issue purchase orders

To learn more about these factors, and how to solve them, check out our infographic on Factors that Impact Your Custom Medical Cart Development Timeline.

Every project is different. Contact us for an estimated timeline on your custom medical cart development project.

New Call-to-action

Topics: Medical Cart Development, Medical Cart Design, Project Management